Project Description

Name: WVJ UPRR Mesquite Automotive Facility
Time-Period: September 28 2015 – December 17 2015
Cost: $675,115.00

Asphalt Removal & Disposal, Asphalt Paving, Concrete Removal & Disposal, Concrete Paving, Pipe Installation

The Scope

The main scope of work includes the following items:

  • Pothole repair
  • 2” asphalt milling, asphalt removal, concrete removal
  • Installation of 8” HDPE pipe and 4 catch basins
  • 2” asphalt overlay, 6” asphalt paving, 10” concrete paving