WSI US 290 Segment 7

Project Description

Name: WSI US 290 Segment 7
Location: Houston, TX
Time Period: July 2013-August 2018
Cost: $63.8 million

US 290 capacity expansion via combination of reconstruction and mainlane widening from 3-1-3 to 5-1-5 lane configuration for 2.5 miles of 290 corridor including major bridge, retaining, paving, storm sewer, removal, etc. via Design-Bid-Build delivery. Project includes multiple major milestones (incentive/disincentive) for expedited delivery amidst high traffic volume and constricted Right of Way. Project requires high-level collaboration between client, design consultants and contractor for expedient resolution of design and utility issues.